Suchman and Darnall Family Dentistry

Tenant Improvement
Bricks and Mortar

Project Details

  • New parking lot, curb and sidewalks - refinish existing secondary lot

  • Alterations to existing facade

  • Architectural Drawings by Guy Gronberg

  • Civil Engineering by Engineering Solutions

  • Completion Cost - $492K

  • Completion Date - Spring 2017

Highlights

  • Demolition of existing lot, curbs, sidewalks

  • Construct new lot, curb and sidewalks and ADA ramp

  • New retention pond

  • Refinish existing secondary lot

  • Exterior upgrades include new tongue and grove siding, stucco, metal roof

  • New entry vestibule